SilverCrest Announces $120MM Project Financing Facility and $76.5MM Fixed Price EPC Contract for Construction of Process Plant

January 04, 2021, 09:05 AM
Filed Under: Industry News

In anticipation of making a final construction decision based on a Feasibility Study  for the Las Chispas Project, SilverCrest Metals Inc. announced that its Canadian subsidiary has entered into a credit agreement (the "Credit Agreement") with an affiliate of RK Mine Finance ("RK") to provide a secured project financing facility (the "Facility") for a total of US$120 million for the purpose of funding the construction of Las Chispas. Concurrently, one of the Company's Mexican subsidiaries has entered into a fixed price Engineering, Procurement and Construction contract (the "EPC Contract") with Ausenco Engineering Canada Inc. ("Ausenco"), and one of its affiliates, for construction of the Las Chispas process plant.

While the Feasibility Study is still pending finalization by Ausenco, with announcement of results targeted for late January 2021, SilverCrest is confident entering into the Credit Agreement and the EPC Contract based on the substantial feasibility information currently available. However, in the absence of a feasibility study of mineral reserves demonstrating economic and technical viability, there is increased uncertainty and historically a higher economic and technical risk of failure associated with the development of a commercially mineable deposit until such time as the Feasibility Study has been completed.

  • The $120 million Facility carries a total cost of capital of approximately 10% (refer to details below);
  • Facility does not require mandatory hedging, cash sweeps, offtakes, production linked payments or equity issuances as part of its structure;
  • $30 million of the Facility has been drawn, and subsequent drawdowns are available upon satisfaction of certain customary conditions precedent. Drawdowns are not tied to any construction milestones;
  • Facility has a four-year term with a 20-month availability period if 50% of the Facility is drawn or committed to be drawn within six months (June 30, 2021) and 75% of the Facility is drawn within 12 months (December 31, 2021);
  • Up to US$30 million of the Facility can be used for exploration and regional acquisitions; and
  • $90 million remaining on the Facility, plus estimated cash at year-end of US$135 million, will provide a substantial component of funding for construction, exploration and regional growth initiatives.

N. Eric Fier, CPG, P.Eng and CEO, remarked, "We are very pleased to have concurrently signed the Credit Agreement and the EPC Contract with two well-established and respected partners in the mining industry. The commitment by both partners ahead of the targeted January 2021 release of the Las Chispas Feasibility Study speaks to the strength of our team and project. While we recognize the challenges of building during this unprecedented time, we believe the strict and effective COVID-19 protocols that we have implemented on site, which are highlighted in these two important agreements, limit our risk. This news marks another important milestone on our path to production at Las Chispas."